Thu Thiem Tunnel three weeks from completion

News/HCMC - Work on the Thu Thiem Tunnel beneath
the Sai Gon River has entered the home stretch and is likely to be completed
next month.
The East – West Highway and Water Environment
Project Management Board and Japanese contractor Obayashi began pouring
concrete to connect the fourth section with the final section on the District 1
side.
A ceremony was held for the purpose on Wednesday
and it was attended by the HCM City Party Committee Secretary Le Thanh Hai, HCM
City People’s Committee Chairman Le Hoang Quan, and Party Committee Deputy
Secretary Nguyen Van Dua.
The head of the board, Luong Minh Phuc, said the
first four sections had been properly installed.
The fourth section was sunk in the river on June 5
after being delivered from Nhon Trach District in neighbouring Dong Nai
Province, where all the sections had been fabricated.
The tunnel is expected to be completed on September
2, the National Day, and connected with the completed East – West Highway next
January.
.:: Other news
• HCM City hands over 620 condos to Thu Thiem residents (12/01/2012)
• Over VND 15,000 billion invested in tunnel systems (10/01/2012)
• HCM City annuls license for Thu Thiem Software Park (09/01/2012)
• Ho Chi Minh City to focus on Thu Thiem Peninsula (21/12/2011)
• HCM City’s Thu Thiem Peninsula to house 86-storey watchtower (19/12/2011)
• Thu Thiem new urban area ready to accept only big investors (15/12/2011)
• HCM City seeks new investors for Thu Thiem Software Park (08/12/2011)
• Ca Mau fertilizer plant nears completion (28/11/2011)
• France helps build Ca Pass tunnel (25/11/2011)